A project to establish a new school in Hulhumale with capacity to accommodate 2000 students.
Project Status
In Progress
Atoll & Island
-
Project Fund
35,000,000.00
Term
01 September 2024
Start Date
01 September 2024
Estimated Completion Date
31 August 2026
Contractor
Eastern Construction Corporation
First floor work commenced
Foundation work completed