National Museum Building Renovation

Project Details

Renovation work is underway for the National Museum, an important center of the country's historical heritage.

Rank

Project Status

Completed

Atoll & Island

-

Project Fund

15,000,000.00

Term

01 March 2023

Start Date

01 March 2023

Estimated Completion Date

31 August 2025

Completed Date

15 August 2025

Contractor

Guraidhoo Investment Private Limited

Update

15 August 2025

Project completed

10 May 2025

Interior design completed

01 November 2024

External building work completed